Viewer: Guest read-only (Viewer)
PROJECT MASTER TRACKER
1. PROJECT DETAILS
Project Name: ABC Residential Building
Location: Chennai
Client: XYZ Developers
Contractor: ABC Constructions
Project Manager : James Folarin (Senior Project Manager)
Start Date: 01-Apr-2024
Planned Finish Date: 31-Mar-2025
2. OVERALL SUMMARY (KPI)
Overall Progress
62%
Schedule Variance
-5
Days
Cost Variance
-2.35%
of Budget
Total Manpower
125
Nos
Open RFIs
8
Nos
Open NCRs
5
Nos
Delayed Activities
7
Nos
Outstanding Bills
1.25
Cr
3. PROGRESS TRACKER
Description Planned % Actual % Variance %
Overall Project 65.00% 62.00% -3%
Sub Structure 100.00% 100.00% 0%
Super Structure 80.00% 70.00% -10%
Masonry 60.00% 45.00% -15%
Plastering 40.00% 25.00% -15%
Flooring 20.00% 10.00% -10%
Finishing 10.00% 5.00% -5%
MEP 15.00% 8.00% -7%
4. ACTIVITY TRACKER
Activity ID Activity Description Planned Finish Actual Finish Status
A101 Excavation 10-Apr-24 08-Apr-24 Completed
A102 PCC 15-Apr-24 14-Apr-24 Completed
A103 Footing 25-Apr-24 26-Apr-24 Completed
A104 Column (G.Floor) 10-May-24 12-May-24 In Progress
A105 Slab (G.Floor) 20-May-24 - Not Started
A106 Column (1st Floor) 30-May-24 - Not Started
5. COST SUMMARY
Particulars Amount (INR)
Total Budget100,000,000
Committed Cost82,000,000
Actual Cost (To Date)61,500,000
Cost Variance-18%
Est. Cost at Completion102,500,000
Forecast Variance2.5%
6. MATERIAL TRACKER
ParticularsQty (MT)
Steel Required850.00
Steel Received620.00
Steel Consumed510.00
Balance110.00
7. MANPOWER TRACKER
CategoryNos
Engineers8
Supervisors12
Skilled Workers78
Unskilled Workers27
Total125
8. QUALITY TRACKER
ParticularsNos
Inspections45
Tests Conducted32
NCRs Raised5
NCRs Closed3
Open NCRs2
9. SAFETY TRACKER
ParticularsNos
Toolbox Talks28
Safety Observations15
Incidents1
Near Miss4
Open Actions3
10. DOCUMENT TRACKER
DocumentStatus
Drawings Approved
Method Statements Approved
Material Submittals In Progress
ITPs In Progress
SOPs Approved